Product A is made from 2 Bs and 1 C.Lead times for A,B,and C are 2,3,and 2 weeks respectively.Currently there are 2 Bs and a 5 Cs on hand,with 5 of each scheduled to arrive at the end of week 1.If 20 As are needed during week 4,can the order be completed (it is the start of week 0 currently)?

Correct Answer

verifed

verified

To produce 20 As requires 40 B...

View Answer

Consider the following product structure. Consider the following product structure.   If the demand for product A is 30 units,and there are 10 units of B on hand and none of C,how many units of part D will be needed? A) 3 B) 40 C) 70 D) 90 E) 110 If the demand for product A is 30 units,and there are 10 units of B on hand and none of C,how many units of part D will be needed?


A) 3
B) 40
C) 70
D) 90
E) 110

F) A) and D)
G) D) and E)

Correct Answer

verifed

verified

In MRP,the number of units projected to be available at the beginning of each time period refers to:


A) net requirements.
B) scheduled receipts.
C) planned order releases.
D) projected on hand.
E) the amount necessary to cover a shortage.

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

The lot-for-lot lot-sizing technique is particularly appropriate when demand is not very smooth and set up cost is small compared to holding cost.

A) True
B) False

Correct Answer

verifed

verified

Reduced inventory levels and faster response to market changes are both benefits of MRP.

A) True
B) False

Correct Answer

verifed

verified

Which lot-sizing technique orders the quantity needed during a predetermined time between orders?


A) economic order quantity
B) periodic order quantity
C) lot-for-lot
D) time fencing
E) part-period balancing

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

You have seen several methods for lot sizing in MRP.Why is lot sizing important in MRP? Can too much concern be given to lot sizing?

Correct Answer

verifed

verified

Lot sizing is important because,at the v...

View Answer

Which of the following is TRUE regarding the POQ lot-sizing method?


A) Each POQ interval is recalculated at the time of the order release.
B) Each order quantity and POQ interval are recalculated at the time of the order release.
C) The POQ interval and all order quantities remain fixed throughout the planning horizon.
D) Each order quantity is recalculated at the time of the order release.
E) POQ lot sizes are always at least as large as the EOQ lot sizes would be.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

A working MRP system allows a firm to react to even minor changes in production requirements.Discuss both the advantage and disadvantage of having such ability.

Correct Answer

verifed

verified

The advantage is that it allows the firm...

View Answer

________ is a lot-sizing technique that generates exactly what is required to meet the plan.

Correct Answer

verifed

verified

Firms may discover that,rather than adapting ERP to the way they do business,they have to adapt the way they do business to accommodate the ERP software.

A) True
B) False

Correct Answer

verifed

verified

Operations splitting sends pieces to the next operation before the entire lot is completed on the previous operation.

A) True
B) False

Correct Answer

verifed

verified

A(n)________ is a bill of material for components,usually subassemblies,that exist only temporarily;they are never inventoried.

Correct Answer

verifed

verified

Phantom bi...

View Answer

Distortion in MRP systems can be minimized when safety stock is held at the:


A) purchased component or raw material level.
B) work-in-process level.
C) finished goods level.
D) A and B
E) A and C

F) B) and C)
G) B) and E)

Correct Answer

verifed

verified

The time-phased product structure,unlike the bill of material,adds the concept of lead times.

A) True
B) False

Correct Answer

verifed

verified

If 100 units of Q are needed and 10 are already in stock,then the gross requirement is 100 and the net requirement is 90.

A) True
B) False

Correct Answer

verifed

verified

The minimum record accuracy required for successful MRP is approximately which of the following?


A) lower than 90%
B) 90%
C) 95%
D) 97%
E) 99%

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Which of the following statements regarding MRP in services is TRUE?


A) MRP is for manufacturing only,and it is not applicable to services.
B) MRP can be used in services,but only in those that offer very limited customization.
C) MRP only works in services for demand that is independent.
D) Services such as restaurant meals illustrate dependent demand,and they require product structure trees,bills-of-material,and scheduling.
E) None of the above is true.

F) D) and E)
G) B) and D)

Correct Answer

verifed

verified

Which of the following best describes a gross material requirements plan?


A) a schedule that shows total demand for an item,and when it must be ordered from a supplier or when production must be started
B) an intermediate range plan for the scheduling of families of products
C) a chart illustrating whether capacity has been exceeded
D) a table that corrects scheduled quantities for inventory on hand
E) a schedule showing which products are to be manufactured and in what quantities

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

A(n)________ provides feedback to the capacity plan,master production schedule,and production plan so planning can be kept valid at all times.

Correct Answer

verifed

verified

closed-loo...